Structural Details: In
this building, the post-tensioned (PT) tendons act similar to beams running
through the concrete slab. When the tension is removed from the cables of the
PT tendons are locked-off, the result is similar to the floor losing its
support beams. The typical solution to this situation is to place shoring under
the affected areas to replace the support. However, in this case, shoring to
support the adjacent bays would interfere with the tenants' business
operations.
Our Approach: Because
of the project constraints, it is possible only if at some place shoring
directly under the slab opening, not under adjacent slabs, as that would result
to less capacity similarly the cables were de-tensioned. This required the
design team to create a phasing plan in which they determined which cables were
allowed to be de-tensioned and in which order. This lock-off phasing plan
allowed the crews to de-tension individual PT tendons, while maintaining the
structural integrity of the entire floor system. The project was phased in
small sections in order to minimize disruption to the existing businesses and
most of the work was performed at night. Once the tendons were re-tensioned,
the crews would begin the concrete demolition for the next lock-off phase. The
total square footage of the project area was 3,600 square feet.