Structure Details: The
deck is 8 in. thick, 2-way, post-tensioned, flat slab. The column-strip
post-tensioning in the E-W direction was inadequate. A repair was developed
using a heavily-reinforced gunite beam added to the underside of the slab
column strip.
Problem: After the repair,
de-lamination between few beams and slab was noticed. An NDT investigation
(pulse velocity test), concluded that approximately 30 percent structure may
have more than 40% de-lamination. The engineering firm then recommended more
NDT inspection utilizing impact echo. Of the 133 beams tested, 105 have showed
some de-lamination, and 19 had 33% or more de-laminated.
Repairing Methodology: The
first phase of the repair included an in-depth and in-situ load testing of the
existing slab under various conditions that existed and strengthened with FRP
sheets. A load testing procedure was proposed to provide a non-destructive
demonstration of the performance of structural components, utilizing hydraulic
jacks to induce force equivalent to those resulting from distributed loads.
Test results indicated that the beam in the E-W
direction with a minimum of 70% bond performed well. A span with no beam
demonstrated poor performance. Results also showed CFRP strengthened slabs
(after removing the Gunite beams) were satisfactory. Accordingly, 19 locations
E-W beams would remove and the slab would be strengthened with CFRP sheet.
Typical span in the N-S direction were found to be acceptable without
additional upgrade. External steel-framing was installed reducing the clear
span, and additional steel supports were installed under the cantilever slabs.
At steel support points, "pancake" jacks were permanently installed
to engage the steel frame.FRP Solution Restores Strength to Skyway Double Tee Beams. Engineers
discovered the presence of numerous hairline cracks in the precast concrete
guide-way beams that support the monorail track nearly a year after the last
segment of the Skyway was completed. An investigation revealed that excessive un-bonding
of the pre-stressing tendons had taken place and caused cracks in 63 of the 500
beams. While the condition was a cause for concern, it posed no immediate
danger to the Skyway. However, temporary supports were installed while a
determination was made on how to repair these cracks. Engineers had developed
five different repair scenarios to address the problem. Repair strategies were
evaluated based on a ranking system that considered durability, maintenance,
aesthetics, and cost. After careful review, the repair strategy selected
involved injection of the cracks and the application carbon fiber reinforced
polymer (FRP).Repairing team had injected all of the cracks, grinded, and
pressure washed the beams. The FRP system was externally bonded onto the ends
of the deficient beams to restore the strength lost due to the un-bonded
strands. Since ensuring the continued operation of the Skyway was important to
the JTA, Structural Preservation Systems developed a strategy to complete the
repairs and upgrades during the evenings and weekends.
No comments:
Post a Comment