Structure Characteristic
The structure consists of three
concrete arches, two piers, two abutments, sidewalk wing walls and parapets. In
addition, the structure is supported on the concrete encased rigid frame.
Problems Incurred:
The roadway was extensively
deteriorated. The arches showed signs of
deterioration as evidenced by a number of leaking cracks and joints. This condition has also indicated a failure
of the deck membrane. In addition to
roadway and arch deterioration movement of the four wing walls required
underpinning. The integrity of the
sidewalls was questionable. Therefore
they were ear marked for demolition. However the removal of the sidewalls
necessitated demolition of the coping and parapets which were in sound
condition.
Inspection / Evaluation:
Essentially a visual examination
revealed the majority problems. However core samples were extracted to identify
and evaluate the overall integrity of the sidewalls
concrete; and establish the methods and material for restoration. Cores were examined visually and microscopically
according to details. Air content and
parameters of air-void system were determined.
Test Results:
Prior to
testing it was appeared that the bridge side-walls required demolition and
replacement. This was as discussed
necessitated removal and replacement of the coping and parapet which were in
sound condition. However, after
excavation and exposure of the inside of the west sidewall a thorough visual inspection was
performed and in conjunction with the results of the core samples it was
determined that the sidewalk
could be repaired using alternate means.
Causes of Deterioration:
The
condition of deterioration damage and disrepair is primarily attributed to the
continuous and arduous use of the structure.
With the necessity to keep open this bridge for vehicular and pedestrian
traffic maintenance was minimal and major repair and restoration was all but prohibitive. However cracking and spalled concrete over
the years required some remedial repairs.
The pre and post-testing program clearly revealed what is common on most
patching and pressure injection repairs.
Core samples show a distinctly un-bonded or poorly bonded patch to the
existing concrete and pressure injected cracks were only partially filled
causing them to open–up or new cracks to occur. It is common knowledge that physical
properties of patching material are often very different from the existing
undisturbed concrete. At the interface perimeter between old and new a high
differential in electro-chemical potential is created. This accelerates corrosion in adjacent steel
reinforcement and consequently the early demise of the concrete patch and surrounding
area. As observed throughout this structure.
Repair Process Execution:
Preparation
required sandblasting
and power washing of the concrete sidewalls. The Resident Engineering
Consultant identified location of cracks marked them on survey drawings and
recorded the length and the width of the defects. Two major materials were recommended to use for vacuum impregnation
repairs on this project: MMA and Low viscosity high modules Epoxy Sealer and Crack Filer. Epoxy Sealer. There are two commonly used methods
to verify the level of success of the repairs - Impact-Echo testing and control coring. 75 mm
and 100 mm cores were taken every 15 meters of discrete cracks. All specimens subjected to testing produced average of
91.25% of the polymer penetration. The compressive strength of three samples
through the cracks increased from 0-800 psi to the average of 3084 psi
which is more than enough for the concrete gravity sidewalk. Borders
between old concrete and patching repairs were sealed up with the repair
polymer.