Structure Characteristics:
The roadway was extensively deteriorated. The arches showed signs of deterioration as
evidenced by a number of leaking cracks and joints. This condition also indicated a failure of
the deck membrane. In addition to
roadway and arch deterioration movement of the four wing walls required
underpinning. The integrity of the
sidewalls was questionable. Therefore
they were ear marked for demolition. However the removal of the sidewalls
necessitated demolition of the coping and parapets which were in sound
condition.
Damage: Essentially
a visual examination revealed the majority problems. However core samples were
extracted to identify and evaluate the overall integrity of the sidewalls
concrete; and determine to establish the methods and material for restoration.
Inspection and
execution: Prior to testing it was appeared, that the
bridge sidewalls required demolition and replacement. As discussed this has necessitated removal
and replacement of the coping and parapet which were in sound condition. However after excavation and exposure of the
inside of the west sidewall a thorough visual inspection was performed and in
conjunction with the results of the core samples it was determined that the sidewalk
could be repaired using alternate means.
The condition of deterioration damage and disrepair is
primarily attributed to the continuous and arduous use of the structure. With the necessity to keep open this bridge
for vehicular and pedestrian traffic maintenance was minimal and major repair
and restoration was all but prohibitive.
However cracking and spilled concrete over the years required some
remedial repairs.
The pre and post-testing program clearly revealed what is
common on most patching and pressure injection repairs. Core samples show a distinctly un-bonded or
poorly bonded patch to the existing concrete and pressure injected cracks were
only partially filled causing them to open–up or new cracks to occur. It is
common knowledge that physical properties of patching material are often very
different from the existing undisturbed concrete. At the interface perimeter
between old and new a high differential in electro-chemical potential is
created. This accelerates corrosion in adjacent steel reinforcement and
consequently the early demise of the concrete patch and surrounding area. As
observed throughout this structure.
Repair executions: Contract documents included
the demolition and replacement of the bridge sidewalls coping and parapet.
However core samples and a thorough visual inspection during the excavation and
exposure of the inside west sidewall determined that process of vacuum
injection / impregnation of concrete repair.Vacuum process on FDR Drive
Reconstruction Project where vacuum grouting delivered a specialty concrete mix
to the forms without any traffic closures.
The implementation of Balvac Process averted the demolition of the
bridge coping and parapet walls which were in relatively sound condition.
Preparation required sandblasting and power washing of the
concrete sidewalls. The Consultant identified location of cracks marked them on
survey drawings and recorded the length and the width of the defects. Two major materials were recommended to use
for vacuum impregnation repairs on this project: MMA and Low viscosity high
modules Epoxy Sealer and Crack Filer. Epoxy Sealer. There are two commonly used
methods to verify the level of success of the repairs - Impact-Echo testing and
control coring. 75 mm and 100 mm cores were taken every 15 meters of discrete
cracks. All specimens subjected to testing produced average of 91.25% of the
polymer penetration. The compressive
strength of three samples through the cracks increased from 0-800 psi to the
average of 3084 psi which is more than enough for the concrete gravity
sidewalk. Borders between old concrete
and patching repairs were sealed up with the repair polymer.
No comments:
Post a Comment